Construction Works Schedule and Location Plans
for Tung Chung New Town Extension (West)
(EP No. EP-519/2016)
December 2025


1. Project Description
The
development of Tung Chung New Town Extension (TCNTE), comprising Tung Chung
East (TCE) and Tung Chung West (TCW), is a mega-scale and complex project
aiming to provide land to meet the future housing economic and social
development needs of Hong Kong. Due to the fact that the proposed works are
geographically separated, the implementation of mega-scale Project is divided
into two packages, namely TCE and TCW respectively. In accordance with the
tight delivery programme, the Project will be implemented in phases under separate
contracts for the developments of TCE and TCW. This Plan only covers the works
in TCW. Construction Works Schedule and Location Plans for TCE can be found at
dedicated project website: http://env.tcnte.hk/ep-submissions.html.
2. Scope of Works for Tung Chung New Town Extension
The Tung Chung New Town Extension project (the Project) comprises the following elements:
(i) reclamation of the seabed by a non-dredged method at TCE to form a total of about 130 hectares of land;
(ii) construction of about 4.9 kilometers of seawalls, with an eco-shoreline, three drainage box culvert outfalls, three circulation drains and a seawater intake at TCE;
(iii) provision of infrastructure for Tung Chung Area 58, including construction of a single two-lane road with a footpath and the associated utility works;
(iv) site formation works at TCW;
(v) construction of the River Park including a visitor centre at TCW;
(vi) construction of proposed open space;
(vii) construction of sustainable urban drainage systems at TCW;
(viii) construction of roads, footpaths, cycle tracks and the associated junction / road improvement works;
(ix) engineering infrastructure works covering drainage, sewerage, waterworks (including a fresh water service reservoir, a salt water service reservoir and a salt water pumping station), common utility tunnels and landscaping works; and
(x)
implementation of environmental mitigation measures and environmental
monitoring and audit programme for the works.
3. Implementation Programme
The
Contract No. NL/2020/05 – Tung Chung New Town Extension – Site Formation and
Infrastructure Works at Ma Wan Chung (i.e. Contract 5) at TCW has been awarded
in May 2021 and the major construction work is scheduled for completion in mid
of 2026. The main contractor for Contract No. NL/2020/05 is Build King – Richwell Civil Joint Venture (BKRCJV).
The
Contract No. NL/2020/06 – Tung Chung New Town Extension – Site Formation and
Infrastructure Works at Tung Chung Valley, Phase 1 (i.e. Contract 6) at TCW has
been awarded in May 2021 and the major construction work is scheduled for
completion in 2026. The main contractor for Contract No. NL/2020/06 is China
Railway Group Limited (CREC).
The
Contract No NL/2023/10 – Tung Chung New Town Extension – Infrastructure Works
at Tung Chung Valley, Yu Tung Road and Ma Wan Chung (i.e. Contract 10) at TCW
has been awarded in October 2025 and is scheduled for completion in 2029. The
main contractor for Contract No. NL/2023/10 is CREC Joint Venture (CRECJV).
The
Entrustment Agreement No. ENT/TUE/001 – Construction of Infrastructure Works in
the Tung Chung New Town Extension Area (i.e. Entrusted Works) has been awarded
in June 2025 and is scheduled for completion in 2028. The main contractor
for Entrusted Works is Bouygues Dragages (1201) Joint
Venture (BDJV).
4. Condition 2.12 of Environmental Permit (EP) for Tung Chung New Town Extension (EP No. EP-519/2016)
The Permit Holder shall, no later than 3 months before the commencement of construction of the Project, deposit 3 hard copies and 1 electronic copy of a work plan (The Plan) with the Director. The Plan shall include at least the following information/specifications:
(i) a detailed phasing programme of all construction works including reclamation, seawall construction, roadworks, river park and sewage pumping stations of the Project; and
(ii)
location plan of all construction works in
an appropriate scale.
5. Submission under EP
In view that only the site formation and infrastructure works at Ma Wan Chung (i.e. Contract 5), Tung Chung Valley, Phase 1 (Contract 6), Area 33 (Entrusted Works) and Infrastructure Works at Tung Chung Valley, Yu Tung Road and Ma Wan Chung (Contract 10) at TCW have commenced, this submission is prepared based on the latest information of Contract 5, Contract 6, Entrusted Works and Contract 10. The submission shall be updated before commencement of construction of the respective contracts for the site formation and infrastructure works or when there is any updated information of the contracts at TCW according to the relevant requirements contained in the EM&A Manual, EIA Report and EP.
The details of Construction Works Schedule and Location Plans for Contract 5 are provided in Attachment I below.
The details of Construction Works Schedule and Location Plans for Contract 6 are provided in Attachment II below.
The details of Construction Works Schedule and Location Plans for Contract 10 are provided in Attachment III below.
The details
of Construction Works Schedule and Location Plans for Entrusted Works are
provided in Attachment IV below.